June 2023
Stripped back to the bones
Inside, the building is stripped back to its bones — the old classrooms gutted to the studs, the school’s original checkerboard floor still down.
Port LaTour · Barrington, Nova Scotia
The Port LaTour Consolidated Elementary School was built in 1956, closed in 2000, and sat empty for more than twenty years. Schoolhouse Rocks bought it in the spring of 2023 and turned it into 15 affordable homes — keeping the building’s bones, and its place in the community. This is that build, in the order it happened.
The Port LaTour Consolidated Elementary School served the community for generations — classrooms, big windows, and a building made to last. It closed in 2000 and sat empty for more than twenty years, while people looked for a place to live.
Schoolhouse Rocks purchased the old school in the spring of 2023, with a plan to turn it into affordable housing rather than let it sit empty. M Nickerson General Contracting led the conversion: framing fifteen new homes inside the old school shell, with new kitchens and bathrooms throughout.
June 2023
Inside, the building is stripped back to its bones — the old classrooms gutted to the studs, the school’s original checkerboard floor still down.
June 2023
The new homes take shape inside the old shell — stud walls rising where classrooms used to be.
September 2023
Demolition work inside — a block wall comes down as the floor plan is opened up for the new homes.
December 2023
The first rooms appear: drywall up, taped and mudded, with the finish work starting.
January 2024
The rebuild in full swing: new stud walls going up inside — the original checkerboard floor still down — while outside the building gets its new roof, Tyvek wrap, windows and doors.
March 2024
The outside takes its finished look: grey siding up top, dark stone below, scaffolding still up.
April 2024
Doors and windows in, the grey siding and stone finished — the building looks like homes now.
May 2024
The last of the inside work — insulation and drywall — while outside the decks and stairs go up.
Completed in 2024, the former school is now 15 affordable one- and two-bedroom homes — four of them wheelchair-accessible, a washer and dryer in every unit, and small decks on the back-wall units. The homes are managed by Carla Lee Property Management, and a community garden is planned for the grounds.
Port LaTour was a school. The next one could be a church, a hall, or a building in your community with no future — Schoolhouse Rocks turns it into homes.
See all our projects at schoolhouserocks.ca